Second and Fourth Street Intersection Improvements Project Updated Timeline
The Second and Fourth Street Intersection Improvements Project has made updates to the website regarding the anticipated timeline of the Project:
The Project timeline has been pushed back approximately 3 months.
Timeline
| Final Design | November/December 2025 |
| Construction Bid Opens for Project | December 2025/January 2026 |
| Construction Bid Closes for Project | January/February 2026 |
| Project Awarded to Contractor by City Council | February/March 2026 |
| Approximate Construction Start | Spring/Summer 2026 |
| A more accurate timeline will be determined based on the weather and contractor availability. |
You can view the new timeline as well as other info here:
https://www.cityofsanrafael.org/second-and-fourth-street-intersection-improvements/